In July of 1996 No 1 blast furnecce was blown in, low smelting intensity had been adopted. In July of 1998 , first strengthening smelting was practiced. Full tuyere operation was adopted. In March of 1999, second strengthening smelting was practiced. Measure of increasing quantity of jetting coal, increasing top gas pressure, ore mixed charging, and stable operation were adopted. Thus utilization coefficient of the blast furnace was increased to 2 0 t/( m 3·d ) up