H. Kotzé,D Bessinger,Johan P. Beukes,Kumba Resources
摘要
Ticor SA began with a detailed feasibility study in 1995. The Hillendale mine (situated between Richards Bay and Empangeni) and Mineral Separation Plant were approved in 2000. The smelter, just outside Empangeni, consists of two 36 MW DC arc furnaces that were commissioned in 200 3. Experiences gained during the initial commissioning of the furnaces proved valuable in later commissioning work, as shown by the increase in ramp-up rates. The capacity of the plant is 250 kt/a TiO2 slag and 145 kt/a of pig iron.