期刊:Management Science [Institute for Operations Research and the Management Sciences] 日期:1967-01-01卷期号:13 (5): 299-306被引量:100
标识
DOI:10.1287/mnsc.13.5.299
摘要
In PERT-type networks, where activity times are random variables, the expected duration of the total project can be approximated by first substituting the expected values of the individual activities, and then evaluating the length of the critical path. This paper develops two improved estimates. Both estimates approach the true expected duration from below, i.e., they are both optimistic estimates.