Hideharu Yonebayashi,T. COLLINS
出处
期刊:SPE Annual Technical Conference and Exhibition
日期:2015-09-23
摘要
Abstract On offshore oil/gas platforms that have no crane equipment, when a slick-line and/or an electrical wire-line job is required, helicopter load/unload operation is a common method for transporting materials such as winch units, power pack units, BOP units, lubricators, etc., from platform or offshore complex to the platform. A series of materials are separately transported by helicopter so that one lifted material can be within the helicopter maximum loading capacity. A package of transportation typically consists of 4-5 load/unload operations for a whole set of materials. Those frequent load/unload operations are done with a hovering action that has the highest risk among a series of helicopter actions (i.e. taking-off, cruising, and approach/landing). To achieve safety, all risk-mitigating factors are adequately incorporated into a plan that should be shared with all crews (pilot, company supervisor, slick-line/wire-line operators) in advance of the operation. In addition to summarizing general safety tips, this paper discusses mitigations from various point of views. As a result of considering ground crew's psychological response based on actual field experience, this paper recommends how to remove these mental factors that silently act on a helicopter marshaller's action. Moreover, fundamental measures are recommended to update marshalling methods and to use new generation helicopters that are designed for improved safety requirements.
科研通智能强力驱动
Strongly Powered by AbleSci AI