Summary for the Renovation of 200 t/d Municipal Solid Waste Incineration Boiler
作者
Liao Hongxing
摘要
Zhuhai Waste Incineration Power Plant(3×200 t/d) had been put into operation since July,2007.At present,the pollutants emission of the MSW incineration system and flue gas disposal system has exceed the requirements of the stipulated standards of China,due to the infancy of the technology of MSW incineration in our country at that time.In order to ensure safety discharge of the MSW boiler,the technical renovation to the municipal solid waste incineration boiler and flue gas disposal equipment was carried out at Zhuhai Waste Incineration Power Plant in 2010,the technical renovation of the boiler was introduced.