According to the technical problems of the borehole gas pressure measurement through the seams under the conditions of the close distance seam group,the long casing pipe with the pressurized grouting technology could be applied to make the borehole drilling and the capsule sticky liquid plug could be applied to seal and measure the borehole pressure.The paper introduced the certain technique process of the pressure measurement borehole construction and the borehole sealing operation steps.When the method applied to measure the gas pressure in E10 seam in Tianan No.10 Mine of Pingdingshan Coal Mining Group,after six days observations,the pressure was stabilized at 2.6 MPa and the gas pressure of the E10 seam was rapidly and accurately measured.The site application conditions showed that the technique method could effectively seal the cracks at the borehole sealing section of the pressure measured borehole through the seams and seal the water system of the aquifer,could prevent the seam section falling of the borehole and isolate the gas connection between the neighbour seams and the pressure measured seam.